Decomissioning and dismantling of
    NPP Obrigheim

    Symposium
    Varna / Bulgarien 2012

    EnBW Kernkraft GmbH
                                        Energie
    Holger Schmidt
1                                       braucht Impulse
    29. Mai 2012
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decommissioning and dismantling of
      NPP Obrigheim

    KWO (Water pressurised                 In sum generated: 90,9 Mrd. kWh
    Reactor / Power: 357 MWel
    Siemens/Westinghouse
    Operational life time:
               1969 - 2005

      Safety decommissioning
      and dismantling
2
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling of
    NPP Obrigheim
    Overview KWO-site220/110 kV   Main controlled
                       FL-SA      area              Monitored area

Storage of                                                     Free release
RAW                                                            equipment

             Head
             quarter

3
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling
NPP KWO
Specifics KWO
• Single unit site                      No further unit, which can deliver services for
                                         the unit under decommissioning

• no dry storage for spent fuel on      New construction required (high effortable
  site (for CASTOR)                      licensing procedure according § 6 AtG with
                                         public hearing, since 2004, up to now no
                                         construction permit issued)

• there is external wet storage         Constructed in the 90th
  for spent fuel on site                 (342 fuel elements), protected against aircraft
                                         impact and operating autonomously

• steam generator tube defects          Activity migration into the secundary circuit,
  (till 1983)                            free releasing procedure required by § 29
                                         StrlSchV for all dismantled material
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling
      NPP Obrigheim
      Main phases

                              1st licence for             Every next step of
                           decommissioning and          dismantling requires a        Free release oo atomic low
                               dismantling                 separate license                     (AtG)

    Operational         Post operational          Decommissioning and                     Conventional
    phase               phase                     dismantling phase                       site cleaning
                      target:                  target:
                      › Spent fuel free        › Shut-down and isolation of systems
                      › Operational media free and components
                      › Chemical desactivation › Dismantling of systems and
                        of Primary circuit       components
                      › Reactor-internal
                        dismantling
     Decommissioning step by step procedure for the controlled area (time critical path!)

     Dismantling of              Dismantling of             Dismantling of       Decontaminati
     contaminated                activated                  remaining            on of concrete
     equipment                   components                 systems              struktures

5    Abbau des Überwachungsbereichs
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling of
    NPP Obrigheim
    Main dismantling steps

1. Dismantling of the equipment in the
                                                2. Dismantling of the equipment in the controlled area
   monitored area

3. Dismantling of activated components of the
            controlled area (remote handling)   4. Dismantling of remaining systems

6
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling of
       NPP Obrigheim
       Licensing procedure

Nachbetriebs-    Stilllegungsphase        Abbau der            Abbau der aktivierten   Abbau der Restanlagen     Gebäude-      Abbau der
phase                                     kontaminierten       Bauteile                                          dekonta-      baulichen
                                          Anlagenteile des                                                       mination      Strukturen
                                          Kontrollbereichs
1. Entsorgung    1. Stillsetzungen von    1. Abbau der         1. Abbau                                          1.            Abbau unter
BE               Systemen                 Großkomponenten      - RDB-Einbauten                                   Aufhebung     AtG und teilw.
                                          (DE, DH,...)         - RDB                                             Kontroll-     konv. Abriss
                                                               - Bioschild                                       bereich
2. Dekonta-      2. Maßnahmen zur         2. Abbau sonstiger                           1. Abbau alter Lüftung,   2. Freigabe
mination von     Senkung der              Anlagenteile ohne                            Abwasserentsorgung,       nach § 29
Komponenten in   Betriebskosten           Restfunktion                                 Kabelpritschen,           StrlSchV
eingebautem      3. Autarkienachweis                                                   Krananlagen u. a.         zwecks
Zustand          externes Nasslager                                                                              nachfolgen-
                 (Notstandsgebäude)                                                                              dem Abriss

3. Medien-       4. Maßnahmen zur                                                      2. Beginn                 3. Boden-
entsorgung       Sicherung des                                                         Gebäudedekonta-           flächen-
                 Reststoffflusses (z.B.                                                mination                  freigabe
                 Materialschleuse)
4. endgültige    5. Anpassung             3. Einbau der        2. Errichtung von       3. Beginn Bodenflächen-
ABN von          Abluftfilterung und      Zerlegeein-          Ersatzanlagen           freimessung
Systemen/Kom-    Abluftüberwachung        richtungen           (Lüftung u.a.)
ponenten
Betriebsge-            1. SAG                  2. SAG                 3. AG            4. AG                                   Entlassung aus
nehmigung        + Änd.Genehmigung        + Änd.Anzeige (B)    + Änd.Genehmigung                                               AtG

 7
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling of
    NPP Obrigheim
    Main activities and time critical path

                                             Alternativer
                                             längerfristiger
                                             Naßlagerbetrieb
                                             (beispielhaft f. 4
                                             a)

                                                   variabel,
                                                   f (Kosten/ a)

8
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Decomissioning and dismantling of
    NPP Obrigheim
    Mass flow overview

9    2011-04-12-ESK
Decomissioning and dismantling of - NPP Obrigheim Symposium Varna / Bulgarien 2012 - International Nuclear ...
Nachbetriebsphase

Post operation phase

                       Energie
                       braucht Impulse
Decomissioning and dismantling of
      NPP Obrigheim
      Post operational phase: Main tasks

  › Cooling of spent fuel
  › Transport of the spent fuel to the external dry storage
  › Flushing and draining of systems, media transport and treatment (sludges,
     resins, water)
  › Chemical desactivation of Primary circuit
  › Reactor-internal dismantling
  › Shut down of non necessary systems
  › Reduction of maintenance and operational testings
  › Inventarisation
  › Radiological classification of systems, components and areas
  › Generation of all necessary papers for 1st apply
  › Start of licensing procedure for decommissioning and dismantling
11›   Plant adaptations
Decomissioning and dismantling of
        NPP Obrigheim
        Post operation phase: Necessary plant adaptations
   Purpose related to:
Decrease post              Upgrate long term Simplify decommissioning Preparate the mass flow
operational costs          remaining         and dismantling          logistic
                           components
- Ersatz großer Anlagen    - Abluftüberwachung   - Vereinfachung der              - Austausch Material-
    durch kleine, mobile   - 100-%-                  Infrastruktur (Heizung,        schleuse zum KB
    (Verdampfer DL-            Abluftfilterung       Kühlwasser, Löschwasser,     - Errichtung Freimessanlage
    Kompressoren           - Kranaufrüstung          Druckluft, elektrischer      - Pufferlagerplätze im ÜB
    Deionaterzeugung)      ...                       Eigenbedarf, Abwasser...)    - Abfalllager
- Systemvereinfachungen                          - Störkantenbeseitigung          - Zementierstation
    und -abstufungen                             - Neuorganisation                - Transportwege
- Anpassung E-                                       Kühlwasser- und Abgabepfad   - 20‘Container-
    Versorgung                                   - Umverlegen verbleibender          Andockstation KB
- Reduzierung von                                    E-Verbraucher/Signale        - LKW-Monitor
    Redundanzen                                      auf wenige Verteiler         - (Nach-)Zerlegeplätzen und
- Fremdversorgung                                ...                                Gebindepufferflächen im KB
    (Heizung, Wäscherei                                                           - Reststoffkonditionierungs-
    u.a.)                                                                           einrichtungen im KB
...                                                                                 (HD-Nasstrahlkabine,
                                                                                    Kabelschredder,...)
   12                                                                             - Interventionsmöglichkeiten
                                                                                    für BA-Konditionierung
Rückblick: Erster Abbauumfang

View backwards: First dismantling step

                                         Energie
                                         braucht Impulse
Decomissioning and dismantling of
     NPP Obrigheim
     1st dismantling step

1. Dismantling of the equipment of the monitored
                                                       2. Abbau kontaminierter Anlagenteile / Kontrollbereich
area

           Antrag: Dezember 2004
          Genehmigung: August 2008

3. Abbau aktivierter Anlagenteile im Kontrollbereich   4. Abbau Restsysteme

14
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Ausbau und Abtransport des Generatorständers

15
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Zerlegung des Speisewasserbehälters

16
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Ausbau und Abtransport des
     Turbinenölbehälters

17
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Ausbau und Entschaufelung der
     Niederdruckturbinen

18
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Abbau der Wasserabscheider-Zwischenüberhitzer

19
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Abbau der Kondensatoren, Freimessen der
     Turbinengehäuse

20
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Ausbau von Kondensator-Rohrbündeln

21
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang: Maschinenhaus -3,2 m
     Vorbereitung zur Nutzung als Pufferlager für leere Endlagerbehälter

22
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Erster Abbauumfang

                                               April 2008
1. Abbau Anlagenteile im Überwachungsbereich

Abbauschritt wurde erfolgreich abgeschlossen   März
                                               2010

23
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Stilllegungsgenehmigung
     Umbau Bau 39/52 zum standorteigenen Zwischenlager für weitgehend
     endlagergerecht verpackte radioaktive Abfälle

24
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Stilllegungsgenehmigung: Abgeschirmter Pufferlagerplatz

25
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Änderung zur Stilllegungsgenehmigung:
     Austausch der Materialschleuse

26
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Änderung zur Stilllegungsgenehmigung:
     Austausch der Materialschleuse

27
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Änderung zur Stilllegungsgenehmigung:
     Austausch der Materialschleuse

28
Stilllegung und Abbau Kernkraftwerk Obrigheim
Änderung zur Stilllegungsgenehmigung:
Austausch der Materialschleuse
Ausblick: Zweiter Abbauumfang

Forward view: 2nd dismantling step

                                     Energie
                                     braucht Impulse
Decomissioning and dismantling of Obrigheim
     2nd dismantling step

1. Abbau Anlagenteile im Überwachungsbereich           2. Dismantling of the equipment of the controlled area

Abbauschritt wurde erfolgreich abgeschlossen                       Application: December 2008
                                                                     License: October 2011

3. Abbau aktivierter Anlagenteile im Kontrollbereich   4. Abbau Restsysteme

31
Decomissioning and dismantling of
      NPP Obrigheim
      2nd dismantling step: time schedule of great component dismantling

      Object
     - Steam generator DE 1                               February 2012
     - Steam generator DE 2
     - Engines of main cooling pumps 1 und 2
     - Main cooling pump 1, Läufer
     - Main cooling pump 1, Pumpengehäuse
     - Main cooling pump 2, Läufer
     - Main cooling pump 2, Pumpengehäuse
     - Main cooling pipe loop 1
     - Main cooling pipe loop 2
     - Pressurizer part 1
     - Pressurizer part 2
     - Pressurizer part 3                                   June 2012

     Contractors: Babcock Noell GmbH and Energiewerke Nord GmbH

32
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Zweiter Abbauumfang: Ausbau der Dampferzeuger

33
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Zweiter Abbauumfang: Vorbereitung der Demontage der
     Dampferzeuger

34
Stilllegung und Abbau Kernkraftwerk Obrigheim
Zweiter Abbauumfang: Ausbau der Dampferzeuger

35
Stilllegung und Abbau Kernkraftwerk Obrigheim
Zweiter Abbauumfang: Ausbau der Dampferzeuger

36
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Zweiter Abbauumfang: Ausbau der Dampferzeuger

37
…und Tschüss

38
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Zweiter Abbauumfang: Vorbereitung der Demontage der
     Hauptumwälzleitung/Setzen der Blindstopfen/Verschluss der HUL

39
Stilllegung und Abbau Kernkraftwerk Obrigheim
     Zweiter Abbauumfang: Abgefrästes Teilstück der Hauptkühlmittelleitung

40
Stilllegung und Abbau Kernkraftwerk Obrigheim
Zweiter Abbauumfang: Ausbau HKMP

41
Welcome for NPP KWO steam generators in
           Greifswald-Lubmin!

42
Ausblick: Dritter Abbauumfang

View forward: 3rd dismantling step

                                     Energie
                                     braucht Impulse
Decomissioning and dismantling of
     NPP Obrigheim
     3rd dismantling step

 1. Abbau Anlagenteile im Überwachungsbereich          2. Abbau kontaminierter Anlagenteile / Kontrollbereich

3. Dismantling of activated components of controlled
                                                       4. Abbau Restsysteme
          area (remote handling)

44
Decomissioning and dismantling of
     NPP Obrigheim
     3rd dismantling step: Dismantling of activated components

     Application for the 3rd dismantling step:        29.03.2010
     Mile stone for expertise:                        June 2012
     Mile stone for license:                          end of 2012

     Adaptation application:      Construction, on-site figuration of the
                                  remote dismantling and packaging
                                  equipment
     Expertise (we got):                              March 2012
     Mile stone for to be approved by authority:      June 2012

     Contractor: Energiewerke Nord GmbH (EWN)
45
Decomissioning and dismantling of
    NPP Obrigheim
    Principles for the planning and licensing procedure
    for remote dismantling of activated components

     Take into account the experience and knowledge from dismantling of
      other performed projects
     Reuse of equipment, which was in successful operation in other
      projects (dismantling and packaging equipment), no experiments!
     Pre-performance of fabrication tests and on-site tests together with
      authority and independent experts (TÜV) on another nuclear place to
      avoid cost intensive 1:1-model dismantling before hot-start
     Equipment design independent from existing plant equipment on-site
     Design and construction for fast assembling and disassembling of
      the additional dismantling and packaging equipment
     Design for reuse in different units
     Comprehensive staff training

                                                                       46
Dismantling parts of the reactor vessel and vessel
                                      internals NPP KWO

                                                                     Top of the vessel

                                                                     Upper core structure

Periphere parts
                                                                     Internal thermal shield

Vessel insolation
                                                                     Reactor vessel

                                                                     Lower core structure

                                                                     Internal base

                                                                                          47
Overview of nessesary dismantling and packaging
                          areas in the reactor building NPP KWO

Wet dismantling area
Room 202 (former                                                Area for other
spent fuel pond)                                                equipment

Packaging area                                                  Nasszerlegebereich
Room 422                                                        Reaktorraum 106/306

                                                                Zerlegebereich für
                                                                periphere Bauteile
                                                                Raum 106

                                                                Trockenzerlegebereic
Area for other                                                  h RDB-Isolierung
equipment                                                       Raum 106/306

                                                                    Packaging area
                                                                    room 208
Dry dismantling area
Room 412

                                                                                     48
Dismantling of activated reactor components
                                               NPP KWO
Room 106/306
 Wet and dry

                  Remote
                                                Dismantling of
                dismantling    Dismantling of
                                                  the RPV-
               and packaging     periphere
                                                    reactor
                 of reactor        parts
                                                  insolation
                 internals

                                                                 Transport
                                                                   of the
                                                                   vessel
                                                                                                  Remote
                                                                             Separation of      dismantling
Room 202

                                                                              of the RPV-     and packaging
                                                                             vessel flange    of the internal
                                                                              and nossel      thermal shield
Wet

                                                                                                                   Transport
                                                                                  zone          + activated
                                                                                                                  of the RPV‐
                                                                                                vessel part          vessel
                                                                                                                    bottom

                                                                              Transport of
                                                                             the flange and
                                                                              nossel zone
Room 412

                                                                                               Dismantling
                Disamantling                                                                                     Dismantling
                                                                                              and packaging
               and packaging                                                                                    and packaging
                                                                                               RPV-flange
                of the RPV-                                                                                      of the RPV-
                                                                                               and nossel
Dry

                 vessel top                                                                                     vessel bottom
                                                                                                  zone

                                                                                                                           49
Shielded containers for packaging of activated
                        dismantled reactor components
                         (CONRAD and MOSAIK)

   Konrad-Container Typ II      Mosaik-Behälter Typ II-15
      Direktbeladung               mit Einsatzkörbe                    Konrad-Container Typ II
                                                                          mit Einsatzkörbe

Konrad-Container Typ IV                              Konrad-Container Typ V
    Direktbeladung                                       Direktbeladung

                                                                                                 50
Resume

         Energie
         braucht Impulse
Decomissioning and dismantling of
      NPP Obrigheim
      Lessons learnt by KWO

     Requirement to reduce the fix costs and the instruction reglement of post operation
 - consequently and permanently!
 Apply the right things on the critical path of project realization!
 Make possible to start the things immediately after getting the license!
       (Many things can be done before – on the level „to be proved“ by authority -
       like installation of new locks, of remote dismantling and packaging equipment …)
 Reduce the number of necessary licensing steps for dismantling!
 The mass flow logistic and disposal strategy are the key points of dismantling!
 Early invite the public to convince them of necessity - you will do!
 Reduce transportation of radioactive material on public streets!
 Disconnect the free releasing procedures from dismantling licensing and check
 them early in reality!
52
German „turn in energy policy“ –
consequences

                                   Energie
                                   braucht Impulse
German government decided the „turn in energy policy“ –
     Immideatly final shut down of 8 NPP +
     Early life time limitation of remaining 9 NPP

        NPP                          life time   life time      new law                               Diese Kraftwerke
                                     gem. Konsens* gem.   AtG**   (2012)                            bleiben abgeschaltet.
        Neckarwestheim I              2011       2019          endgültige Abschaltung (final shut-down)
        Philippsburg 1                2012       2020          endgültige Abschaltung                             Brunsbüttel
        Isar 1                        2011       2019          endgültige Abschaltung
                                                                                                                         Krümmel
        Unterweser                    2012       2020          endgültige Abschaltung
                                                                                                    Unterweser
        Biblis A                      2011       2019          endgültige Abschaltung
        Biblis B                      2012       2020          endgültige Abschaltung
        Brunsbüttel                   2012       2020          endgültige Abschaltung
        Krümmel                       2019       2033          endgültige Abschaltung
        Grafenrheinfeld               2015       2028          2015                                 Biblis A, B
        Gundremmingen B               2015       2030          2017
        Philippsburg 2                2018       2032          2019
        Gundremmingen C               2016       2030          2021                                               Philippsburg 1
        Grohnde                       2018       2032          2021
                                                                                            Neckarwestheim I                    Isar 1
        Brokdorf                      2019       2033          2021
        Isar 2                        2020       2034          2022
        Emsland                       2021       2034          2022
54      Neckarwestheim II             2022       2036          2022
     *Konsens 2001/ Rot– Grüne Bundesregierung   **AtG 2011/schwaz-gelbe Bundesregierung / entspr. verfügbarer Reststrommengen gemäß BfS
After moratorium: Energy market is changing in Germany
Situation in the German power grid January - May 2011
(Quelle: Bundesnetzagentur, Daten: ENTSO-E)
Impact of Renewable Energy sources on the profitness
     of all other energy generators – the operating time and the
     covered percentage of required power decreases

                     €/MWh
                                                           required              nuclear
                                                            power                Brown coal
                                                                                 Black coal
       Without RE

                                                                                 Natural gas
                                                                                 oil
                    M1
                     €/MWh

                                       M1 >> M2
       With RE

                    M1
                    M2
                             RE
56                                                    available capacity in GW
Challange: Profitability
     New built projects increase the pressure on existing power plants –
     Overview new built coal fired plants

       Expected grid connection
      Informationen aus allgemein zugängliche Quellen, wie Zeitungsberichten
      und Aussagen aus dem Markt; Stand: 09.11.2011)
                                                                                                                            Datteln, Block 4
                                                                                                                            Fertigstellung offen

     10.000 MW                                                                                                         Mannheim, GKM 9

                                                                                                  Karlsruhe, RDK 8

                                                                                    Lünen, Stummhafen
     8.000 MW
                                                                                 Westfalen, Block E

                                                                               Walsum, Block 10
     6.000 MW
                                                                        Wilhelmshaven

                                                                Westfalen, Block D

                                                                Moorburg, Block B
     4.000 MW

                                             Neurath, BoA 3

                                         Moorburg, Block A
     2.000 MW

              Neurath, BoA 2
                                                                                                                            Brown coal

          Boxberg, Block R                                                                                                  Black coal

      10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
        2011                        2012                                            2013                             2014                          2015
57
The planned encrease of Renewable Energy is a big
        problem for profitability of all other plants

               40
                                                          Entwicklung der erneuerbaren Energien in Deutschland
                    Quellen:
                    Daten 1990 bis 2010: AG Energiebilanzen, Stand 10.05.2011
                    Daten 2020: Hintergrundinformationen zum Ausbau der EE in Deutschland bis 2020", Mai 2011                                       217 Mrd. kWh
               35

               30

               25               Hausmüll
                                Geothermie
     Prozent

                                Photovoltaik
               20               Biomasse
                                Windkraft
                                                                                                                   103 Mrd. kWh
                                Wasserkraft
               15

                                                                                                                                                   Onshore

               10

               5                                                                                                                                   Offshore

               0
                    1990      1992       1994      1996       1998       2000      2002       2004       2006   2008   2010   2012   2014   2016     2018     2020
58
Consequenses of the „turn in energy policy“- grid extension!
dena-Netzstudien I+II zum Netzausbau in Deutschland
Windkraftanlagen

                                                      Offshore-Windpower potential
 Grid
 extension                                            till 2030:
 2008 bis 2012                                        +8 bis +17 GW

 Necessary grid
 extension                                            Repowering Onshore-
 2012 bis 2015                                        Windpower potential till 2020:
                                                      +10 bis +15 GW
 Energy
 consumption
 centers
                                                      Required is a serios grid
                                                      extension – especially in North-
                                                      South-direction!

                                                      No remarkable power extension
                                                      by RE in the South of Germany

59
                                                                           Quelle: BdEW (2010)
Consequenses of the „turn in power policy“
     for EnBW (EnKK)

                                Greatest Challange for the future:
                                       Parallel activities of
                                operation and decommissioning /
                                           dismantling

     Safety and profitability          Safety and profitability      Safety and profitability
     of 2nd units operation                 of 1st units                 of dismantling
         GKN II / KKP 2                  decommissioning                 of NPP KWO
                                          GKN I / KKP 1

60
Vielen Dank für Ihre Aufmerksamkeit!

   Thank you for your attention!

                                       Energie
                                       braucht Impulse